Rio Tinto cuts 2021 iron ore shipments forecast on labour squeeze

Must read

Stock Markets6 minutes ago (Oct 14, 2021 09:06PM ET)

(C) Reuters. The Rio Tinto logo is displayed on a visitor’s helmet at a borates mine in Boron, California, U.S., November 15, 2019. REUTERS/Patrick T. Fallon/Files

MELBOURNE (Reuters) -Rio Tinto Group on Friday reduced its 2021 iron ore shipments forecast, as a tighter labour market in Western Australia delayed the completion of a new greenfield mine at Gudai-Darri.

“It has been another difficult quarter operationally and … we recognise the opportunity to raise our performance,” said chief executive officer Jakob Stausholm.

The miner now expects 2021 Pilbara iron ore shipments at between 320 million tonnes (mt) and 325 mt, down from a previous range of 325 mt to 340 mt.

The downgrade puts Rio on course to lose its spot as the world’s biggest iron ore producer to Brazilian rival Vale S.A..

“Another disappointing quarter for Rio Tinto (NYSE:RIO) as the company struggles to regain operational momentum,” broker RBC said in a research note.

Rio said a tight global supply chain added to its difficulties, while headwinds from China’s regulatory tightening could spark further volatility.

Iron ore prices have nearly halved since hitting a record peak in mid-May, with demand hurt by China’s steel output curbs and a sharp slowdown in the country’s property activity due to a regulatory crackdown. [IRONORE/]

Still, Rio shipped 83.4 mt of the steel-making commodity in the three months ended Sept. 30, 2% higher than the 82.1 mt shipped last year.

However, Pilbara iron ore production was 4% lower, hurt by heritage management, brownfield mine replacement tie-ins and project completion delays.

Rio’s destruction of the 46,000 year-old Juukan Gorge rock shelters last year had led to a leadership overhaul of the company and a national inquiry.

Rio also delayed first production for the Oyu Tolgoi copper mine in Mongolia by three months to January 2023. Joint venture partner, Canada’s Turquoise Hill Resources (NYSE:TRQ), on Thursday estimated additional funding required for the project had ballooned to $3.6 billion.

Delays to development of what will be one of the world’s largest copper mines has antagonised the Mongolian government, which owns a 34% stake, and fuelled a funding spat between Rio and Turquoise Hill.

Rio Tinto shares were down 1% in morning trade in a slightly firmer broader market.

Rio Tinto cuts 2021 iron ore shipments forecast on labour squeeze

Disclaimer: Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. All CFDs (stocks, indexes, futures) and Forex prices are not provided by exchanges but rather by market makers, and so prices may not be accurate and may differ from the actual market price, meaning prices are indicative and not appropriate for trading purposes. Therefore Fusion Media doesn`t bear any responsibility for any trading losses you might incur as a result of using this data.

Fusion Media or anyone involved with Fusion Media will not accept any liability for loss or damage as a result of reliance on the information including data, quotes, charts and buy/sell signals contained within this website. Please be fully informed regarding the risks and costs associated with trading the financial markets, it is one of the riskiest investment forms possible.

Latest article

Subscribe to our newsletter

To be updated with all the latest news, offers and special announcements.